ARCHITECTS | ENGINEERS | COST FORM FOR EQUIPMENT



ARCHITECTS| ENGINEERS| COST FORM FOR EQUIPMENT
Estimate de Daily value for  Equipment and vehicles 
for a Construction Projects



Cost Form for Equipment



Under the reforms or new projects that we're trading, we need to quantify the type and amount of vehicles for transfer of Staff, General utility trucks (e.g.| For the supply of potable water for irrigation, domestic transport of materials etc.), So we need to know, with good approximation, the daily cost of this Construction Equipment
This applies also to the Road Machinery, Cranes, Concrete Plant, Motorcycle welders, Current Generators, etc.. ... Whether the expenditure is charged to any direct cost action (e.g.| Road equipment Soil Movement) or overheads
To assign these costs relatively quickly we need to know


-The lifetime of the equipment (use tables for this, or just use the experience)
-Original Value Construction Equipment
-Resale cost of equipment at the end of its useful life (may be zero)
-The Depreciated-Construction Equipment cost (the difference between the actual cost and resale value)

- Average-value of Equipment (depreciated value divided by 2)
-Annual Interest-current
-Fuel Cost per liter
-The yield of Equipment by a Unit of Measure (UM)

Daily cost-loads the staff concerned at the same (in the case of a vehicle will be his driver in the case of a Concrete Plant Operator will be the expert and some helpers)

With these data in hand, we fill it on the attached sheet and get the daily Construction -Equipment cost
Daily Depreciation = Value to depreciate x 8h x day / lifetime in hours

Daily Interest Cost of Capital = average value x value annual Team x 8 hours of annual use day/2000hours

The daily cost of repairs and parts = 50% of the costs of amortization of every day

Daily fuel cost = 0.15 liters of fuel x HPHS x number of HP x 8h x price of fuel

Daily Cost of Lubricants = 40% the price of oil per day

Daily Cost of Labor = Cost of Manpower (plus social security charges) by the daily percentage of participation of Manpower

Monitoring cost = 10% of labor price per day of Surveillance

Overheads = 12% of the total cost per day

The daily cost of Construction Equipment = Sum of the partial costs

Dear readers, one’s next entry, we will stay in budget stuff and see OVERHEAD-PART 3